Amulet Development Offshore Project Proposal

 

Project name: 

Amulet Development 

                   

A745429

Submitted by:

KATO Energy 

                   

Titles:

WA-8-L

                   

Submission type:

New

                   

Status: 

Closed for comment

                   

Website: 

katoenergy.com.au

                   

Project description

 The Amulet Development is within Commonwealth waters in retention lease WA-8-L, located ~132 km north of Dampier in the north-west of Australia, in water depths of ~80 m.  The Talisman oil field is ~3.5 km to the west of Amulet, within WA-8-L, the field has already been produced, but was abandoned 1992. Due to its proximity to the Amulet field, KATO may choose to reinstate production from the Talisman field concurrently with the Amulet Development.

KATO Energy Pty Ltd (KATO) plans to develop the Amulet and Talisman fields using a relocatable system known as the ‘honeybee production system’.

The honeybee production system has been used successfully in many locations around the world, including offshore WA. The ‘honeybee production system’ comprises the following key elements:

  • jack-up mobile offshore production unit (MOPU).
  • production unit on the MOPU, which will separate and process oil, gas and water.
  • wells workover module on the MOPU, which will have the capability to plug and abandon wells, and potentially to drill; however, a separate mobile offshore drilling unit (MODU) may be used.
  • short flowline and riser from the MOPU to a catenary anchor leg mooring (CALM) buoy.
  • floating marine hose to transport oil.
  • moored floating storage and offloading (FSO) facility, where oil is stored; or direct to shuttle tankers (depending on export option selected).
  • floating export hose to offload oil from the FSO to export tankers.

The key components covered in this Offshore Project Proposal (OPP) for the Amulet Development are:

  • site survey of the proposed location of subsea infrastructure
  • drilling of up to two production wells, one dual-purpose production/water injection well, and allowance for a sidetrack
  • installation, hook-up and commissioning of a mobile offshore processing unit (MOPU), catenary anchor leg mooring (CALM) buoy and mooring arrangements, flowline and riser, and a floating storage and offloading (FSO) facility
  • operation of the facilities
  • decommissioning and removal of subsea and surface infrastructure, and plug and abandonment (P&A) of the wells.

If the Talisman oil field is developed, up to two production wells will be drilled with allowance for a sidetrack. The preferred field development option is to drill extended reach deviated wells through the conductor deck of the MOPU, whilst at the Amulet location. However, if a subsea tieback system option is selected, the following additional components will be incorporated specifically for the development of the Talisman field:

  • Talisman subsea trees (production wells) and jumpers to the manifold
  • Talisman manifold, to commingle production from nearby Talisman wells
  • ~3.5 km production flowline and service umbilical from the Talisman manifold to the MOPU at Amulet.

Amulet and Talisman fields are part of a portfolio of KATO operated fields. The intent is that as each field is depleted, it is fully decommissioned, and the honeybee production system is then relocated to the next field.

The conservative project life for the Amulet Development (from mobilisation to decommissioning) is approximately five years, with a preliminary project schedule outlined in the table below.

OPP documents 

The proposal can be downloaded using the links below:

Draft for public comment - Amulet Development Offshore Project Proposal- Rev 2 - September 2019 (PDF 64MB)

Proponent contact for further enquiries

KATO Energy Development Manager 

Brett MacRae 

Phone: +61 8 9320 4700

Emailinfo@katoenergy.com.au

Mailing address: 102 Forrest Street Cottesloe, Western Australia 6000              

Quick links

Introduction to Offshore Project Proposals

Community Information

Making public comment on offshore project proposals information paper (PDF 239KB)

Offshore project proposal assessment policy (PDF 288KB)

Brochure - Offshore petroleum environmental approvals - July 2020 (PDF 5.9MB)


Stay informed about Offshore Project Proposals by subscribing to NOPSEMA updates here.

Phase

Timing*

Indicative Duration

Survey

Q1 2023

1 month

Drilling

Initial campaign – Q2/Q3 2023

Second campaign (if required) – 1 to 2 years after start-up

Initial campaign – 7 months

Second campaign (if required) – additional 4 months 

Installation, Hook-up and Commissioning

Q3 2023

3 months

Operations

Q4 2023

Between 1.5 and 4.5 years, at best and high estimates of production respectively

Decommissioning

Between 2025 and 2027

(depending on duration of operations)

3 months

*Timing shown is if the Amulet Development is the first field developed using the relocatable honeybee production system of the KATO-owned fields. 

If the KATO-owned fields are developed in a different order, the timing of Amulet may be later than shown.