East Spar Inspection and Removal

Back to Search Subscribe

Activity name
East Spar Inspection and Removal
Activity types
Significant modification of a petroleum pipeline
Submitted by
Quadrant Oil Australia Pty Limited
Submission date
30/05/2018
Submission type
New
Status
EP not in force
Decision date
16/07/2018
Related documents
EP Summary (pdf 1.5 MB)

Location map (click to enlarge)
A612768
Progress bar
Submission
Assessment
Final decision
EP summary published
Activity started
Activity stopped
End of operation of EP
Activity events
Event Event date Next event* Next event due* Related documents
Submission of new EP 30/05/2018 NOPSEMA decision 29/06/2018 Not applicable
Request for further information 19/06/2018 Titleholder action 10/07/2018 Not applicable
Submission of further information 05/07/2018 NOPSEMA decision 19/07/2018 Not applicable
Acceptance of EP 16/07/2018 Titleholder action 26/07/2018 Decision notification (pdf 9.5 MB)
Submission of EP summary 26/07/2018 NOPSEMA decision 06/08/2018 Not applicable
Publication of EP summary 02/08/2018 Not applicable Not applicable

* The next event is based on NOPSEMA’s understanding and expectation of what may occur next in the assessment process. There are a number of other events that may occur, and events may happen sooner or later than expected. All events will be published in this table as and when they take place.

Activity description

Quadrant Oil Australia Pty Ltd (QOA) is the registered operator for Petroleum Production Licence WA-13-L in offshore Commonwealth waters on the North West Shelf (NWS) of Western Australia (WA). QOA is 100% owned subsidiary of Quadrant Energy Australia Ltd (Quadrant). Quadrant proposes to install infrastructure required to perform intelligent pigging (inspection) activities of the East Spar system, and remove flowlines and associated infrastructure which are at the end of design life and no longer used in production.

 

The East Spar Inspection and Removal activities will be carried out using a Dive Support Vessel (DSV) or Installation Support Vessel (ISV).  Installation of infrastructure is required to allow intelligent pigging activities to inspect the East Spar system, prior to removal of flowlines and associated infrastructure of the East Spar 1, 3 and 6 Production System.

Regions
North West
Commonwealth waters adjacent to
Western Australia
Titles (or other instruments)
WA-13-L Opens in new window
Contact

Mr Tim Robinson

HSE Manager - Operations and Projects

Level 7, 100 St Georges Terrace

PERTH WA 6000

Telephone: +61 8 6218 7100

Email: HSE.Regulatory@quadrantenergy.com.au

Reference
4522

*Where an environment plan was submitted or accepted prior to 28 February 2014 certain information is not published, in accordance with the Environment Regulations in place at that time. For accepted EPs, refer to the attached EP Summary for additional information.